Physically Server Maintenance
Scheduled Maintenance Report for Millersville University
Completed
The scheduled maintenance has been completed.
Posted Jun 08, 2020 - 19:33 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 08, 2020 - 18:01 EDT
Update
We will be undergoing scheduled maintenance during this time.
Posted Jun 08, 2020 - 11:42 EDT
Update
We will be undergoing scheduled maintenance during this time.
Posted Jun 08, 2020 - 11:41 EDT
Update
Max will not be available until server move is completed.
There are limited functionalities for ancillary systems which depend on MAX.
Posted Jun 08, 2020 - 11:22 EDT
Scheduled
Physical servers in rack MR-6 will be shut down and moved in order to create the room needed for the new hyper-converged Cisco hardware. Servers include: Coal, BANNERWEBNEW, MUAD4, MUAD3, Mars, MU-Files, and an Avimar DataDomain Host.
Posted Jun 02, 2020 - 12:01 EDT
This scheduled maintenance affected: Banner (Banner 9).