Backup server maintenance - production site

Scheduled Maintenance Report for Millersville University

Completed

The upgrade was completed successfully.
Posted Nov 05, 2019 - 10:38 EST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 05, 2019 - 09:00 EST

Scheduled

The Data Domains, which store the server backups taken by Avamar, will be upgraded on Monday, 11/4 and Tuesday, 11/5. The upgrade will begin at approximately 9AM each day. The schedule and impact is:

Monday, November 4 – Upgrade begins on the Shippensburg side. There will be no impact to scheduled backups. The go/no go decision for Tuesday will be made upon completion.

Tuesday, November 5 – Upgrade begins on MU side. There will be minimal impact to daytime-running backups.
Posted Nov 01, 2019 - 11:08 EDT